A review shows only minor movement in the implementation of the Murray-Darling Basin Plan (MDBP) in the past 6 months.
The latest assessment of progress says that some important elements are at risk or unlikely to be achieved by the June 2024 deadline.
Murray-Darling Basin Authority (MDBA) chief Andrew McConville concedes that progress in some areas has been overshadowed by lack of advancement in others.
“The Basin Plan needs to be fully implemented if it’s to achieve the outcomes we’re seeking for a healthy and sustainable Basin for all communities. It is becoming clear what will and won’t be achieved by June next year,” Mr McConville says.
The MDBA’s latest progress report card provides a picture of the status and progress on five areas of the Basin Plan: water resource plans, water recovery, Sustainable Diversion Limit (SDL) adjustment mechanism measures, Northern Basin initiatives and the delivery of water for the environment.
“Since the July 2022 report card, we have seen some progress with 4 New South Wales water resource plans accredited for groundwater resources. However, the dial remains firmly on the red because there is still a way to go to get all the WRPs accredited,” Mr McConville said.
“The dial for some projects under the Sustainable Diversion Limit adjustment mechanism also remains on red. Of the 36 supply and constraints projects, 22 are likely to be operable, 8 are on the cusp of delivery and 6 will not be delivered as originally proposed by 30 June 2024.
“We’ve seen positive outcomes from good planning and delivery of environmental water across the Basin - this is critically important and underpins the very foundation of the Basin Plan to support the health of rivers, floodplains and wetlands.
“The focus of the past 6 months has been to support bird breeding events and to improve water quality where floods have resulted in low oxygen levels.”
Mr McConville said some of the northern Basin toolkit measures in the northern Murray-Darling Basin were running behind schedule, with one measure in particular highly unlikely to be delivered on time.
“These important initiatives are intended to protect water for the environment, improve compliance with water laws and create opportunities for local communities, including First Nations People. It is in everyone’s interest that greater headway is made towards completing the northern Basin toolkit measures.”
The full report is accessible here.